- A total of 611,231 meters have been deployed as at January 31, 2021 under the Meter Asset Provider initiative since its full operation despite the COVID-19 pandemic and other extraneous factors, the Nigerian Electricity Regulatory Commission has said.
A total of 611,231 meters have been deployed as at January 31, 2021 under the Meter Asset Provider initiative since its full operation despite the COVID-19 pandemic and other extraneous factors, the Nigerian Electricity Regulatory Commission has said.
NERC disclosed this in a consultation paper on the review of the MAP Regulations.
The proposed review of the MAP scheme is coming nearly four months after the Federal Government launched a new initiative called National Mass Metering Programme aimed at distributing six million meters to consumers free of charge.
“The existence of a huge metering gap and the need to ensure successful implementation of the MYTO 2020 Service-Based Tariff resulted in the approval of the NMMP, a policy of the Federal Government anchored on the provision of long-term low interest financing to the Discos,” NERC said.
The commission had in March 2018 approved the MAP Regulations with the aim of fast-tracking the closure of the metering gap in the sector through the engagement of third-party investors (called meter asset providers) for the financing, procurement, supply, installation and maintenance of meters.
It set a target of providing meters to all customers within three years, and directed the Discos and the approved MAPs to commence the rollout of meters not later than May 1, 2019.
But in February 2020, NERC said several constraints, including changes in fiscal policy and the limited availability of long-term funding, had led to limited success in meter rollout.
NERC, in the consultation paper, highlighted three proposed options for metering implementation going forward.
The first option is to allow the implementation of both the NMMP and MAP metering frameworks to run concurrently; the second is to continue with the current MAP framework with meters procured under the NMMP supplied only through MAPs (by being off-takers from the local manufacturers/assemblers).
The third option is to wind down the MAP framework and allow the Discos to procure meters directly from local manufacturers/assemblers (or as procured by the World Bank), and enter into new contracts for the installation and maintenance of such meters.
“Customers who choose not to wait to receive meters based on the deployment schedule of the NMMP shall continue to have the option of making upfront payments for meters which will be installed within a maximum period of 10 working days,” NERC said.
The regulator said such customers would be refunded by the Discos through energy credits, adding that there would be no option for meter acquisition through the payment of a monthly meter service charge.
“Where meters have already been deployed under the meter service charge option, Discos shall make one-off repayment to affected customers and associated MAPs. Such meters shall be recognised in the rate base of the Discos,” it added.
NERC urged stakeholders to provide comments, objections, and representations on the proposed amendments within 21 days of the publication of the consultation paper.